Weekly Project Update
PfISD LTC

Nathan Stanford
Dec 24, 2025
THIS WEEK'S ACCOMPLISHMENT
- More flooring installed
- More electrical work installed. Very late!
- More A/C grilles installed. Some missing
- Baffle ceilings installed
- Some glass for Demountable Walls Some missing
- Welding scheduled for Friday 08 changes

Flooring in main area started
NEXT WEEK'S ACTIVITIES
- Finish up welding and inspection on 08
- Start 08 sheet rock changes
- Last of flooring installs
- More store front frames/doors install
- Final coat paint starts

- Electrical all over continues. Late!
Special ceilings installation continues

Baffles installed and protected from dust
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.