Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Aug 1, 2025

THIS WEEK'S ACCOMPLISHMENT

    Started to install cement back board in rest room, but put on hold pending more changes.
    Started to install framed hard sheet rock ceilings for rough in but got put on hold.
    Sheet rock continues in areas we passed inspection last week "C" and "A"
    Tracks for folding partitions installed. Big step. Now can finish framing around them
    Ductwork continues in "B" area
    Electrical work continues all over including changes added to MDF type rooms
Excavation 1.jpg

Cement backer board for tile in bathrooms started. Hold pending changes

NEXT WEEK'S ACTIVITIES

    Sheet rock continues Insulation continues
    Tape and float continues
    Still holding on hard ceilings and tile backer board for rest room change decisions
    Duct work continues on "B" Should be 90% of entire job by end of this week. Exception is CRAC area
    Electrical pulling wire all over. Rough in changes continue.
Excavation 1.jpg
    Minor a/c items on roof to begin.

Some framing for sheet rock ceiling started.

Excavation 1.jpg

Folding partition track installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.