top of page


Weekly Project Update
PfISD LTC

Nathan Stanford
Aug 1, 2025
THIS WEEK'S ACCOMPLISHMENT
- Started to install cement back board in rest room, but put on hold pending more changes.
- Started to install framed hard sheet rock ceilings for rough in but got put on hold.
- Sheet rock continues in areas we passed inspection last week "C" and "A"
- Tracks for folding partitions installed. Big step. Now can finish framing around them
- Ductwork continues in "B" area
- Electrical work continues all over including changes added to MDF type rooms

Cement backer board for tile in bathrooms started. Hold pending changes
NEXT WEEK'S ACTIVITIES
- Sheet rock continues Insulation continues
- Tape and float continues
- Still holding on hard ceilings and tile backer board for rest room change decisions
- Duct work continues on "B" Should be 90% of entire job by end of this week. Exception is CRAC area
- Electrical pulling wire all over. Rough in changes continue.

- Minor a/c items on roof to begin.
Some framing for sheet rock ceiling started.

Folding partition track installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page