Weekly Project Update

PfISD LTC

Placeholder

Pat Tims

Oct 23, 2025

THIS WEEK'S ACCOMPLISHMENT

    Started wall ceramic tile in bathrooms
    Started cloud ceiling grid minus the missing light fixtures and special acoustical ceilings parts.
    Continued the low voltage electrical rough in VERY LATE!
    Continued with exterior painting
    Air Conditioning grilles started in ceiling grid areas.
    Plumbing started hot water heater in riser room.
Excavation 1.jpg

Lots of wires hanging for future items in ceiling grid

NEXT WEEK'S ACTIVITIES

    Ceiling grid continues in all areas
    Cabinets start setting
    Ceramic tile continues
    Low voltage wiring continues VERY LATE!
    Cable trays continue with some wiring in "C" area to start.
Excavation 1.jpg
    Start more floor sealing.

Exterior painting continues

Excavation 1.jpg

Ceramic wall tile continues.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.