THIS WEEK'S ACCOMPLISHMENT
- Started wall ceramic tile in bathrooms
- Started cloud ceiling grid minus the missing light fixtures and special acoustical ceilings parts.
- Continued the low voltage electrical rough in VERY LATE!
- Continued with exterior painting
- Air Conditioning grilles started in ceiling grid areas.
- Plumbing started hot water heater in riser room.

Lots of wires hanging for future items in ceiling grid
NEXT WEEK'S ACTIVITIES
- Ceiling grid continues in all areas
- Cabinets start setting
- Ceramic tile continues
- Low voltage wiring continues VERY LATE!
- Cable trays continue with some wiring in "C" area to start.

- Start more floor sealing.
Exterior painting continues

Ceramic wall tile continues.