Weekly Project Update
PfISD LTC

Nathan Stanford
Sep 26, 2025
THIS WEEK'S ACCOMPLISHMENT
- Started cable trays
- Started ceiling grid
- Wiring continues
- Work on owner changes above ceiling
- Tape/float/paint "A" area started
- Started a/c grilles in ceilings with ceiling grid.

Grid started in "C" area
NEXT WEEK'S ACTIVITIES
- Epoxy CRAC rooms area
- Wiring continues all over
- Tape and float continue in "A" and start in "B" areas
- Sprinkler riser completes.
- Layout of special ceilings continues

- Start on added column wrap changes
Panels wiring in main electrical room

Cable trays started
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.