THIS WEEK'S ACCOMPLISHMENT

    Started cable trays
    Started ceiling grid
    Wiring continues
    Work on owner changes above ceiling
    Tape/float/paint "A" area started
    Started a/c grilles in ceilings with ceiling grid.
Excavation 1.jpg

Grid started in "C" area

NEXT WEEK'S ACTIVITIES

    Epoxy CRAC rooms area
    Wiring continues all over
    Tape and float continue in "A" and start in "B" areas
    Sprinkler riser completes.
    Layout of special ceilings continues
Excavation 1.jpg
    Start on added column wrap changes

Panels wiring in main electrical room

Excavation 1.jpg

Cable trays started