THIS WEEK'S ACCOMPLISHMENT
- Started tape and float on area "C"
- Roof top units wired ready for startup next week.
- All sheet rock walls installed in area "B"
- Refrigerant lines hooked up to roof top units for startup next week.
- Electrical rough in continues on lights and some added plugs.
- Started painting exterior

Exterior doors painted 1st coat prior to installing hardware
NEXT WEEK'S ACTIVITIES
- Sheet rock on ceilings due to begin.
- Paint on area "C" due to start.
- Roof top unit due to have factory start up commence.
- Inspection on B & A
- Paint on MDF and IDF to start.

- Cable trays to start in "C" area.
Area "C" started tape and float of walls

Plywood on MDF and IDF rooms has started