THIS WEEK'S ACCOMPLISHMENT

    Started tape and float on area "C"
    Roof top units wired ready for startup next week.
    All sheet rock walls installed in area "B"
    Refrigerant lines hooked up to roof top units for startup next week.
    Electrical rough in continues on lights and some added plugs.
    Started painting exterior
Excavation 1.jpg

Exterior doors painted 1st coat prior to installing hardware

NEXT WEEK'S ACTIVITIES

    Sheet rock on ceilings due to begin.
    Paint on area "C" due to start.
    Roof top unit due to have factory start up commence.
    Inspection on B & A
    Paint on MDF and IDF to start.
Excavation 1.jpg
    Cable trays to start in "C" area.

Area "C" started tape and float of walls

Excavation 1.jpg

Plywood on MDF and IDF rooms has started