Weekly Project Update
PfISD LTC

Nathan Stanford
Oct 10, 2025
THIS WEEK'S ACCOMPLISHMENT
- Slowly getting black paint on deck prep done. Delayed 3 weeks
- Electrical getting caught up on above ceiling work
- One set of store front frames installed. 2 more to go.
- 75% of CRAC duct installed. Waiting on pieces to finish
- Exterior door and hardware started installing.
- Lots of ceiling wires and Unistrut installing before black paint occurs.

Cable tray installing all over. Some pending black paint above.
NEXT WEEK'S ACTIVITIES
- More ceiling preparation continues
- More exterior frames and hardware install
- Electrician trying to make up lost time above ceiling. Changes working to complete.
- Painting continues on exterior
- Ceiling grid continues to install

- Ceramic tile scheduled to deliver and start install Area "A" large bathrooms.
Exterior doors and hardware started.

Data center ceiling and grilles starting to install. Pending electrical.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.