THIS WEEK'S ACCOMPLISHMENT

    Slowly getting black paint on deck prep done. Delayed 3 weeks
    Electrical getting caught up on above ceiling work
    One set of store front frames installed. 2 more to go.
    75% of CRAC duct installed. Waiting on pieces to finish
    Exterior door and hardware started installing.
    Lots of ceiling wires and Unistrut installing before black paint occurs.
Excavation 1.jpg

Cable tray installing all over. Some pending black paint above.

NEXT WEEK'S ACTIVITIES

    More ceiling preparation continues
    More exterior frames and hardware install
    Electrician trying to make up lost time above ceiling. Changes working to complete.
    Painting continues on exterior
    Ceiling grid continues to install
Excavation 1.jpg
    Ceramic tile scheduled to deliver and start install Area "A" large bathrooms.

Exterior doors and hardware started.

Excavation 1.jpg

Data center ceiling and grilles starting to install. Pending electrical.