THIS WEEK'S ACCOMPLISHMENT
- Large curbs for roof A/C unit arrived and sat on roof. Crane required.
- New gear arrived and installed. Waiting on ONCOR to reenergize new gear.
- More sheet rock all areas. Expansions joints got approved and starting to install.
- Duct connections to roof units started
- Old exterior expansion joint caulking in exterior wall starting to remove and new material installed
- Window that have glass caulking completed. Some are still waiting glass.

Sheet rock continues in all areas. This is area where large TV may install.
NEXT WEEK'S ACTIVITIES
- Complete new gear change over and re-start power
- Metal coping on roof started
- Roof top units should sit on curbs. Crane again.
- Continue sheet rock all areas
- Continue conduit and wire pulling all areas

- Start hooking up power to roof units
Sheet rock to deck for sound finally approved and started.

Large roof top unit curbs arrived and set with crane
LOOK AHEAD SCHEDULE