top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Aug 28, 2025

THIS WEEK'S ACCOMPLISHMENT

    Large curbs for roof A/C unit arrived and sat on roof. Crane required.
    New gear arrived and installed. Waiting on ONCOR to reenergize new gear.
    More sheet rock all areas. Expansions joints got approved and starting to install.
    Duct connections to roof units started
    Old exterior expansion joint caulking in exterior wall starting to remove and new material installed
    Window that have glass caulking completed. Some are still waiting glass.
Excavation 1.jpg

Sheet rock continues in all areas. This is area where large TV may install.

NEXT WEEK'S ACTIVITIES

    Complete new gear change over and re-start power
    Metal coping on roof started
    Roof top units should sit on curbs. Crane again.
    Continue sheet rock all areas
    Continue conduit and wire pulling all areas
Excavation 1.jpg
    Start hooking up power to roof units

Sheet rock to deck for sound finally approved and started.

Excavation 1.jpg

Large roof top unit curbs arrived and set with crane

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page