THIS WEEK'S ACCOMPLISHMENT
- Tape and float area "C"
- Started tape and float area "A"
- Last of exterior window glass arrived and installed.
- Downspouts completed
- Rough in of electrical changes started. Lots of these, more to come.
- Exterior door frame replacement started.

Downspouts completed
NEXT WEEK'S ACTIVITIES
- Continue to tape and float areas A and start in B
- Cable trays start installing
- Exterior doors and frames install continues.
- Storefronts are due to ship this week and start installing.
- Electrical changes continue

- Dry fall painting high at deck to start.
Area "C" tape and float 95% complete