THIS WEEK'S ACCOMPLISHMENT

    Tape and float area "C"
    Started tape and float area "A"
    Last of exterior window glass arrived and installed.
    Downspouts completed
    Rough in of electrical changes started. Lots of these, more to come.
    Exterior door frame replacement started.
Excavation 1.jpg

Downspouts completed

NEXT WEEK'S ACTIVITIES

    Continue to tape and float areas A and start in B
    Cable trays start installing
    Exterior doors and frames install continues.
    Storefronts are due to ship this week and start installing.
    Electrical changes continue
Excavation 1.jpg
    Dry fall painting high at deck to start.

Area "C" tape and float 95% complete

Excavation 1.jpg

Area "A" started tape and float.