THIS WEEK'S ACCOMPLISHMENT

    The interior portion of supply ducring has been installed
    Aircraft has punched through fer the supply duct and has connected to the exterior
    B&L recutting the return hole
    Climatec ran the wires for their sensors
    Aircraft has ran the break off ducts to office, bathrooms, and closets
    Moved the RTU 6" to proper location
Excavation 1.jpg

Interior Supply duct

NEXT WEEK'S ACTIVITIES

    Finishing install of break off ducts
    Return duct instillation
    Hook up and power all sensors for Climatec
    B&L installing the trimming to the around the return
    21st century paint will be painting after drywall and duct is done
Excavation 1.jpg
    Fencing around the RTU

Return hole being recut

Excavation 1.jpg

Break off into bathroom

LOOK AHEAD SCHEDULE