THIS WEEK'S ACCOMPLISHMENT
- First coat of paint applied to area C
- Area A framing started
- Corridor ceilings framing complete
- Corridor ceilings sheet rock started
- Utility tie in to manhole complete
- Area B two side sheet rock 90% complete

Utility line from building to man hole
NEXT WEEK'S ACTIVITIES
- Begin to first coat paint area B
- Complete plumbing top-out
- One side sheet rock area A
- Complete two layers of sheet rock on corridors
- Backfill utility line trench in parking lot

- Pull wire for area C
First coat of paint in Area C

Corridor ceilings sheet rock started and walls taped/floated