Weekly Project Update
RR Fire Station 10

Richard Huddleston
Jul 4, 2025
THIS WEEK'S ACCOMPLISHMENT
- Installed batter boards on building pad.
- Delivered storm RCP, HDPE, and manholes.
- Delivered wastewater pipe and manholes.
- Potholed existing water main and curb inlet pipe to verify elevation for flow from the new pond.
- Past density on first lift of general fill at parking area.
-

Processing general fill for parking area.
NEXT WEEK'S ACTIVITIES
- Install storm Manholes and RCP on south drive to pond.
- Begin installation of plumbing drains on building pad.
- Complete second lift and test at parking area.
- Dirt contractor demobilize.
- Begin electrical underground

-
Unloading wastewater pipe.

Delivering storm RCP.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.