Weekly Project Update

RR Fire Station 10

Placeholder

Richard Huddleston

Jul 4, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed batter boards on building pad.
    Delivered storm RCP, HDPE, and manholes.
    Delivered wastewater pipe and manholes.
    Potholed existing water main and curb inlet pipe to verify elevation for flow from the new pond.
    Past density on first lift of general fill at parking area.
Excavation 1.jpg

Processing general fill for parking area.

NEXT WEEK'S ACTIVITIES

    Install storm Manholes and RCP on south drive to pond.
    Begin installation of plumbing drains on building pad.
    Complete second lift and test at parking area.
    Dirt contractor demobilize.
    Begin electrical underground
Excavation 1.jpg

Unloading wastewater pipe.

Excavation 1.jpg

Delivering storm RCP.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.