THIS WEEK'S ACCOMPLISHMENT
- Installed foundation reinforcement
- Installed building Ufer ground
- Installed trench drains in Apparatus bays
- Installed anchor bolts in the living quarters area
- Design team and consultants pre pour inspections
-

Trench drains installation.
NEXT WEEK'S ACTIVITIES
- Lightening protection installation
- Clean up around building pad prepping for concrete placement
- Third party pre pour inspection
- CMU in slab dowels installation
- Pour foundation at living quarters Gridlines 1-10

-
Design team and consultants pre pour inspection.

Foundation reinforcement going in.
LOOK AHEAD SCHEDULE