Weekly Project Update

RR Fire Station 10

Placeholder

Richard Huddleston

Aug 22, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed foundation reinforcement
    Installed building Ufer ground
    Installed trench drains in Apparatus bays
    Installed anchor bolts in the living quarters area
    Design team and consultants pre pour inspections
Excavation 1.jpg

Trench drains installation.

NEXT WEEK'S ACTIVITIES

    Lightening protection installation
    Clean up around building pad prepping for concrete placement
    Third party pre pour inspection
    CMU in slab dowels installation
    Pour foundation at living quarters Gridlines 1-10
Excavation 1.jpg

Design team and consultants pre pour inspection.

Excavation 1.jpg

Foundation reinforcement going in.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.