top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

RR Fire Station 10

Placeholder

Richard Huddleston

Jun 30, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed compacted subgrade under heavy duty paving west and south of the building.
    Completed building pad.
    Completed low P I material mining from the pond to use as general fill under paving.
    Staked building corners and utilities.
Excavation 1.jpg

Importing select fill for building pad.

NEXT WEEK'S ACTIVITIES

    Set batter boards.
    Complete shaping of the pond.
    Complete subgrade east of the building pad, and parking area.
    Deliver storm material.
    Begin underground utility installation.
Excavation 1.jpg

Staked building corners and utilities.

Excavation 1.jpg

Site

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page