Weekly Project Update
RR Fire Station 10

Richard Huddleston
Jun 30, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed compacted subgrade under heavy duty paving west and south of the building.
- Completed building pad.
- Completed low P I material mining from the pond to use as general fill under paving.
- Staked building corners and utilities.
-
-

Importing select fill for building pad.
NEXT WEEK'S ACTIVITIES
- Set batter boards.
- Complete shaping of the pond.
- Complete subgrade east of the building pad, and parking area.
- Deliver storm material.
- Begin underground utility installation.

-
Staked building corners and utilities.

Site
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.