top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

RRISD Great Oaks ES

Placeholder

Ian Doyle

THIS WEEK'S ACCOMPLISHMENT

    Finished Cleaning South Wing Classrooms
    Finished Cleaning Admin Wing Offices
    Finished Installing HVAC Roof Top Units
    Continued Start Up of HVAC Units / All Areas
    Continued Re-Installing Ceiling Grid and Tile / Admin Wing
    Started Turning Areas Over to Janitorial Staff
Excavation 1.jpg

Natural Gas Line Roughed In on Roof B1

NEXT WEEK'S ACTIVITIES

    Finish Start Up of HVAC Units / All Areas
    Finish Re-Installing Ceiling Grid and Tile / Admin Wing
    Finish Final Cleaning
    Finish Fixing Punch List Items
    Finish Turning Areas Over to Janitorial Staff
Excavation 1.jpg
    Start Mobilizing Off Site

Install of Exhaust Fan Transitions Complete

Excavation 1.jpg

Roof Top HVAC Unit Installed on Roof B1

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page