Weekly Project Update
RRISD Great Oaks ES

Ian Doyle
THIS WEEK'S ACCOMPLISHMENT
- Finished Cleaning South Wing Classrooms
- Finished Cleaning Admin Wing Offices
- Finished Installing HVAC Roof Top Units
- Continued Start Up of HVAC Units / All Areas
- Continued Re-Installing Ceiling Grid and Tile / Admin Wing
- Started Turning Areas Over to Janitorial Staff

Natural Gas Line Roughed In on Roof B1
NEXT WEEK'S ACTIVITIES
- Finish Start Up of HVAC Units / All Areas
- Finish Re-Installing Ceiling Grid and Tile / Admin Wing
- Finish Final Cleaning
- Finish Fixing Punch List Items
- Finish Turning Areas Over to Janitorial Staff

- Start Mobilizing Off Site
Install of Exhaust Fan Transitions Complete

Roof Top HVAC Unit Installed on Roof B1
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.