Weekly Project Update

Santa Rita MS Portables Connection

Placeholder

Brady Staedtler

Jul 25, 2025

THIS WEEK'S ACCOMPLISHMENT

    New carpet installed
    Security cameras installed on portables
    Data network setup and online to all portables
    Maintenance began moving furniture into portables after fire inspection was approved
Excavation 1.jpg

Data network up and running for all portables

NEXT WEEK'S ACTIVITIES

    Begin cleanup at SRMS and LHES
    Begin to put fences up at all 3 schools
    Finish getting PA systems connected
Excavation 1.jpg

New carpet installed

Excavation 1.jpg

Furniture being moved into portables

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.