Weekly Project Update
Santa Rita MS Portables Connection

Brady Staedtler
Jul 25, 2025
THIS WEEK'S ACCOMPLISHMENT
- New carpet installed
- Security cameras installed on portables
- Data network setup and online to all portables
- Maintenance began moving furniture into portables after fire inspection was approved
-
-

Data network up and running for all portables
NEXT WEEK'S ACTIVITIES
- Begin cleanup at SRMS and LHES
- Begin to put fences up at all 3 schools
- Finish getting PA systems connected
-
-

-
New carpet installed

Furniture being moved into portables
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.