THIS WEEK'S ACCOMPLISHMENT

    Completed demo and poured all new concrete at LHES
    New fire hydrant passed inspection
    3 new basketball goals set at LHES
Excavation 1.jpg

New basketball goals poured and set at LHES

NEXT WEEK'S ACTIVITIES

    Install new carpet inside portable at SRMS
    Get all portables connected to data and security cameras installed
    PA systems connected in all portables
    Clean up at both sites
    Fencing put back up at all 3 schools
Excavation 1.jpg
    New striping at LHES

Completed demo of island and began pouring new concrete

Excavation 1.jpg

Completion of all new concrete at LHES