THIS WEEK'S ACCOMPLISHMENT
- Started grading ad putting up forms for new sidewalks
- Demo'd damaged curb that will be replaced
- Power connected and on to all portables
-
-
-

Began grading and setting forms for new sidewalks
NEXT WEEK'S ACTIVITIES
- Pour new sidewalks
- Begin running fiber to portables
- Gegin demo on ceiling tiles
- Begin demo on island at LHES
-

-
All cables pulled for connection from main electrical panel to new transformer

Power connected and on to all portables
LOOK AHEAD SCHEDULE