top of page


Weekly Project Update
Santa Rita Portables Connection 06-27-2025

Brady Staedtler
Jun 27, 2025
THIS WEEK'S ACCOMPLISHMENT
- Began grading and putting up forms for new sidewalks
- Demo'd damaged curb for it to be replaced
- Power connected and on to all Portables
-
-
-

Grading and forms being set for new sidewalks
NEXT WEEK'S ACTIVITIES
- Pour new sidewalks
- Begin running fiber to all portables
- Begin demo on ceiling tiles
- Begin demo on island at LHES
-

-
All cables pulled for connection from main electrical panel to new transformer

Power connected and on to all portables
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.