THIS WEEK'S ACCOMPLISHMENT

    Poured new sidewalks for access to portables
    Finished removal of fire lane striping at LHES
Excavation 1.jpg

Finished fire lane removal at LHES

NEXT WEEK'S ACTIVITIES

    Have new fiber network setup in new portables along with new pathways being hung
    Start demo on damaged ceiling tiles in portables
    Start demo on existing island at LHES
Excavation 1.jpg

Excavation 1.jpg

New sidewalks poured for access to portables at SRMS