top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Spicewood ES

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Started classroom air conditioners on 300,400, & 500 wing.
    Completed roof hydrant installation.
    Reinstalled light fixtures in main corridors.
    Began moving furniture in classrooms.
    Installed electrical panels DPA and HVA
    Started RTU 5 that supplies the gym.
Excavation 1.jpg

Patched VCT and installed cove base in corridors 200,300,400, & 500.

NEXT WEEK'S ACTIVITIES

    Startup the balance of the air conditioning equipment.
    Complete above ceiling inspections.
    Start installation of the FRL wainscoting trim.
    Complete fixture and toilet accessories
    Final inspections
Excavation 1.jpg
    Final clean corridors and restrooms

Restroom fixtures.

Excavation 1.jpg

Toilet partitions in renovated restrooms.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page