top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

SRMS Portables Connection

Placeholder

Brady Staedtler

Aug 8, 2025

THIS WEEK'S ACCOMPLISHMENT

    Fences at all 3 schools put back up
    Striping at LHES completed
    New roofing put on portables at LHES completed
    New ramp installed between portables at LHES
    New coil installed for cooling tower at LHHS
Excavation 1.jpg

Fencing put back up at LHES

NEXT WEEK'S ACTIVITIES

    Complete fencing at LHHS and LHES
    Bollards by new fire hydrant to be installed
    Complete PA system installation at SRMS
    Start drain piping at LHHS
Excavation 1.jpg

New ramp system installed at LHES

Excavation 1.jpg

New roofing for portables at LHES

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page