Weekly Project Update
SRMS Portables Connection

Brady Staedtler
Aug 8, 2025
THIS WEEK'S ACCOMPLISHMENT
- Fences at all 3 schools put back up
- Striping at LHES completed
- New roofing put on portables at LHES completed
- New ramp installed between portables at LHES
- New coil installed for cooling tower at LHHS
-

Fencing put back up at LHES
NEXT WEEK'S ACTIVITIES
- Complete fencing at LHHS and LHES
- Bollards by new fire hydrant to be installed
- Complete PA system installation at SRMS
- Start drain piping at LHHS
-

-
New ramp system installed at LHES

New roofing for portables at LHES
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.