Weekly Project Update

SRMS Portables Connection 08/01/2025

Placeholder

Brady Staedtler

Aug 1, 2025

THIS WEEK'S ACCOMPLISHMENT

    Began installing PA systems and getting all portables connected to main building
    Cleaned up and finished final grading at SRMS
    Cleaned up and finished final grading at LHES
Excavation 1.jpg

Cleanup at LHES

NEXT WEEK'S ACTIVITIES

    Fences to be put back up at all 3 schools
    Build new ramp system at LHES
    Complete PA system setup at SRMS
    New blinds to be installed in SRMS portables
Excavation 1.jpg

Final grading at LHES

Excavation 1.jpg

Cleanup and final grading completed at SRMS

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.