Weekly Project Update
ST LOUIS CATHOLIC CHURCH 7/11/2025

Robert Chaison
Jul 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- All electrical troubleshooting complete final lighting programming happening next week and training
- Painters cleaning up and preparing all areas for final coat
- East parking lot paved and sod is in for majority of the site
- Bathroom partitions are in and done
- all hardware in except for a change order of new items for adjustment of fit.
-

paving in, sod is down aswell
NEXT WEEK'S ACTIVITIES
- continue final coat and clean of painters
- start the prep for the floors in reception area and classroom carpet install
- cabinets install starting Monday should be complete by Thursday or Fiday.
- counter top install for the breakroom
-

-
partitions are in and done

cabinets for the breakroom have arrived and ready for install on Monday
LOOK AHEAD SCHEDULE