Weekly Project Update

ST LOUIS CATHOLIC CHURCH 7/11/2025

Placeholder

Robert Chaison

Jul 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    All electrical troubleshooting complete final lighting programming happening next week and training
    Painters cleaning up and preparing all areas for final coat
    East parking lot paved and sod is in for majority of the site
    Bathroom partitions are in and done
    all hardware in except for a change order of new items for adjustment of fit.
Excavation 1.jpg

paving in, sod is down aswell

NEXT WEEK'S ACTIVITIES

    continue final coat and clean of painters
    start the prep for the floors in reception area and classroom carpet install
    cabinets install starting Monday should be complete by Thursday or Fiday.
    counter top install for the breakroom
Excavation 1.jpg

partitions are in and done

Excavation 1.jpg

cabinets for the breakroom have arrived and ready for install on Monday

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.