Weekly Project Update

ST LOUIS CHURCH 7/25/2025

Placeholder

Robert Chaison

Jul 25, 2025

THIS WEEK'S ACCOMPLISHMENT

    CARPET TILES ARE COMPLETE
    BASE BOARD INSTALLED READY FOR PUDDY AND PAINT
    REFRESH OF THE WEST DECK FOR PATIO STARTED
    ALL ELECTRICAL AND LIGHGTING TROUBLSHOOTING COMPLETE
Excavation 1.jpg

CABINET UPPER AND LOWERS ARE IN, WAITING FOR COUNTERTOPS.

NEXT WEEK'S ACTIVITIES

    TRANSACTION WINDOW INSTALL AND MAIN STOREFRONT COMPLETION
    CONTNINUE DECK TOP AND DIRT WORK AROUND
    REMOVE FLOOR PROTECTION AND EVALUATE FLOOR FOR NEEDED TOUCHUP AND REPAIR
    AWAIT THE ARRIVAL OF THE BREAKROOM EQUIPMENT
    FINAL PAINT OF ENTIRE SITE
Excavation 1.jpg

DECK RE-WORK IS UNDERWAY

Excavation 1.jpg

CARPET AND BASE BOARD IS INSTALLED.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.