THIS WEEK'S ACCOMPLISHMENT

    FINAL BIT OF HARDWARE INSTALLED
    ALL PATCH WORK COMPLETED STARTED FINAL PAINT FOR ENTIRE PROJECT
    REMOVAL OF ALL UNUSED MATERIALS AND EQUIPMENT
Excavation 1.jpg

NEW EAST COURTYARD DECK IS IN AND WAITING ON RAILING

NEXT WEEK'S ACTIVITIES

    AXIS COMING OUT TO FINISH ANY WORK LEFT FOR FRONT SIDEWALK AND CURBS THAT WHERE REMOVED
    ALL SECURITY WORK TO BE COMPLETED
    ALL NEW SMOKE DEVICES WILL BE INSTALLED IN EXISTING OFFICES TO COMPLETE FIRE INSTALL AND PROGRAMMING
    HANDRAILS AND DECORATIVE PERIMETER FENCING INSTALL TO START
Excavation 1.jpg

ALL FLOOR PROTECTION UP AND WAITING FOR CLEANING

Excavation 1.jpg

MAIN ENTRY HARDWARE INSTALLED GOT THIS PLACE ALL SECURED NOW