THIS WEEK'S ACCOMPLISHMENT
- FINAL BIT OF HARDWARE INSTALLED
- ALL PATCH WORK COMPLETED STARTED FINAL PAINT FOR ENTIRE PROJECT
- REMOVAL OF ALL UNUSED MATERIALS AND EQUIPMENT
-
-
-

NEW EAST COURTYARD DECK IS IN AND WAITING ON RAILING
NEXT WEEK'S ACTIVITIES
- AXIS COMING OUT TO FINISH ANY WORK LEFT FOR FRONT SIDEWALK AND CURBS THAT WHERE REMOVED
- ALL SECURITY WORK TO BE COMPLETED
- ALL NEW SMOKE DEVICES WILL BE INSTALLED IN EXISTING OFFICES TO COMPLETE FIRE INSTALL AND PROGRAMMING
- HANDRAILS AND DECORATIVE PERIMETER FENCING INSTALL TO START
-

-
ALL FLOOR PROTECTION UP AND WAITING FOR CLEANING

MAIN ENTRY HARDWARE INSTALLED GOT THIS PLACE ALL SECURED NOW
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.