Weekly Project Update
TCESD 2 STATION 6
THIS WEEK'S ACCOMPLISHMENT
- Concrete Paving Blue Tops
- Approaches Saw Cut & Removed
- Concrete Paving Layout
-
-
-

LQ Truss Progress
NEXT WEEK'S ACTIVITIES
- LQ Trusses
- Concrete Paving Forms
- Concrete Paving Reinforcing Steel
- Concrete Paving 1st Pour
-

-
East Side Storm Pipe Complete

Paving Blue Tops Underway
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.