THIS WEEK'S ACCOMPLISHMENT

    Structural Steel Mobilized
    AB Approaches
    CMU Walls
    LQ Exterior Framing
    LQ Electrical Wall Rough
    LQ Plumbing Wall Rough
Excavation 1.jpg

AB Structural Steel Underway

NEXT WEEK'S ACTIVITIES

    Retaining Wall Excavation
    AB Approach Concrete Placement
    Retaining Wall Forms
    AB Roof Decking
    LQ Structural Columns
Excavation 1.jpg

AB Approach Reinforcing Steel

Excavation 1.jpg

Progressing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.