Weekly Project Update

TCESD 2 STATION 6

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    GB Concrete Placement at AB
    Oil Separator Tank Installed
    GB Forms Wrecked at AB
    AB Soil Retainers Underway
    AB Backfill Getting Started
Excavation 1.jpg

Oil Separator Tank Installed

NEXT WEEK'S ACTIVITIES

    LQ Termite Pre Treat
    LQ Void Forms & Vapor Barrier
    LQ Slab Reinforcing Steel
    AB Under Slab Plumbing Rough In
    AB Under Slab Electrical Rough In
Excavation 1.jpg

Wastewater Line Landscaping

Excavation 1.jpg

AB Grade Beams Ready to Backfill

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.