THIS WEEK'S ACCOMPLISHMENT

    Building Pad Complete
    Site Grading Ready For Utilities
    Eagle Eye Building Corners & Pier Layout
    Detention Outfall Material On Site
Excavation 1.jpg

Outfall Material Moving In

NEXT WEEK'S ACTIVITIES

    Start Detention Pond Outfall
    Batter Board Install
    Pier Reinforcing Material
    Start Drilling Piers
    Start Detention Outfall Pipe
Excavation 1.jpg

Weiss Lane Entrance

Excavation 1.jpg

Building Layout Underway

LOOK AHEAD SCHEDULE