Weekly Project Update

TCESD 2 STATION 6

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    Masonry Walls Started
    Downspout Storm Pipe
    AB Concrete Sanded & Densifier Applied
    LQ Exterior Framing Started
    Drive & Parking Lot Reinforcing Steel On-site
Excavation 1.jpg

CMU Walls Going Up

NEXT WEEK'S ACTIVITIES

    AB Approach Forms & Reinforcing Steel
    Retaining Wall Excavation
    Exterior Metal Stud Framing
    CMU Walls AB
    Electrical Rough In CMU Walls
Excavation 1.jpg

AB Floor Sanding

Excavation 1.jpg

LQ Walls Underway

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.