THIS WEEK'S ACCOMPLISHMENT

    Void Forms at LQ
    Vapor Barrier at LQ
    Reinforcing Steel at LQ
    Plumbing Cast in Place Set
    Electrical Floor Boxes and Conduits
Excavation 1.jpg

Plumbing Cast in Place Set

NEXT WEEK'S ACTIVITIES

    Concrete Placement at LQ
    Wreck Forms at LQ
    Termite Pre-Treat at AB
    Void Forms at AB
    Vapor Barrier at AB
Excavation 1.jpg
    Reinforcing Steel at AB

Electrical Floor Boxes Set

Excavation 1.jpg

Ready for Concrete Placement