top of page


Weekly Project Update
TCESD 2 STATION 6
THIS WEEK'S ACCOMPLISHMENT
- Void Forms at LQ
- Vapor Barrier at LQ
- Reinforcing Steel at LQ
- Plumbing Cast in Place Set
- Electrical Floor Boxes and Conduits
-

Plumbing Cast in Place Set
NEXT WEEK'S ACTIVITIES
- Concrete Placement at LQ
- Wreck Forms at LQ
- Termite Pre-Treat at AB
- Void Forms at AB
- Vapor Barrier at AB

- Reinforcing Steel at AB
Electrical Floor Boxes Set

Ready for Concrete Placement
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page