Weekly Project Update
The Learning Center eanes isd

Martin Diaz
Jul 26, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Framing of hard lids on the 1st floor, fur downs and any remaining hard lid soffits
- complete tape and bed and painting on 1st floor hard lids
- complete the installation of light fixtures and fire devises.
- Eanes subcontractors completed the in install of low voltage, TV's, clock and speakes.
- Fire alarm contractor programming fire alarm devise. Shunt trip completed, ceiling devise completed. Duct detectors hook up completed
- Exterior fence completed,

Main entrance at the 1st floor lobby area
NEXT WEEK'S ACTIVITIES
- Monday the 28th meeting will Fire tron, Capitol sprinklers, Duval electric and prologic to check all devises to make sure it all functions properly
- call for inspections and finals
- Complete the concrete stoop
- Complete the remaining door hardware, both interior and exterior.
- Storefront on 1st floor office installed

- Complete punch list
2nd floor lobby area

Hallways between classrooms
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.