Weekly Project Update

The Learning Center eanes isd

Placeholder

Martin Diaz

Jul 26, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Framing of hard lids on the 1st floor, fur downs and any remaining hard lid soffits
    complete tape and bed and painting on 1st floor hard lids
    complete the installation of light fixtures and fire devises.
    Eanes subcontractors completed the in install of low voltage, TV's, clock and speakes.
    Fire alarm contractor programming fire alarm devise. Shunt trip completed, ceiling devise completed. Duct detectors hook up completed
    Exterior fence completed,
Excavation 1.jpg

Main entrance at the 1st floor lobby area

NEXT WEEK'S ACTIVITIES

    Monday the 28th meeting will Fire tron, Capitol sprinklers, Duval electric and prologic to check all devises to make sure it all functions properly
    call for inspections and finals
    Complete the concrete stoop
    Complete the remaining door hardware, both interior and exterior.
    Storefront on 1st floor office installed
Excavation 1.jpg
    Complete punch list

2nd floor lobby area

Excavation 1.jpg

Hallways between classrooms

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.