Weekly Project Update
The Learning Center eanes isd

Martin Diaz
Jul 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- all 2x4 light fixtures installed. All outlet J-boxes in ceiling covered
- Partial overhead inspection passed for ceiling border installation
- Painter complete 2nd coat of paint on the 2nd floor
- Carpet in 2nd floor classrooms in progress
- Fire alarm company installation of fire alarm device in progress
- Doors for the new classrooms have been matched with the classrooms

Bathroom accessories installed for new bathrooms
NEXT WEEK'S ACTIVITIES
- 1st floor 2nd coat paint or finish coat of paint
- 1st floor installation of floors in progress
- FDC in riser room installed.
- Call for overhead inspection for both floors
- Cover all ceiling of both floors

- Hard lid ceiling tape and float and paint.
Classroom accessories installed in each classroom

2nd coat of paint 2nd floor
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.