top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

The Learning Center eanes isd

Placeholder

Martin Diaz

Jul 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    all 2x4 light fixtures installed. All outlet J-boxes in ceiling covered
    Partial overhead inspection passed for ceiling border installation
    Painter complete 2nd coat of paint on the 2nd floor
    Carpet in 2nd floor classrooms in progress
    Fire alarm company installation of fire alarm device in progress
    Doors for the new classrooms have been matched with the classrooms
Excavation 1.jpg

Bathroom accessories installed for new bathrooms

NEXT WEEK'S ACTIVITIES

    1st floor 2nd coat paint or finish coat of paint
    1st floor installation of floors in progress
    FDC in riser room installed.
    Call for overhead inspection for both floors
    Cover all ceiling of both floors
Excavation 1.jpg
    Hard lid ceiling tape and float and paint.

Classroom accessories installed in each classroom

Excavation 1.jpg

2nd coat of paint 2nd floor

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page