Weekly Project Update

The Learning Center Eanes isd

Placeholder

Martin Diaz

Jun 30, 2025

THIS WEEK'S ACCOMPLISHMENT

    Asphalt patch work on private road. Underground water line completed all the way to Camp craft. One test remaining.
    Both floors Casework is in progress.
    Bathrooms tile work on 1st floor complete
    Ceiling grid on 2nd floor minus stair area and the water fountain is complete
    1st floor and 2nd floor 1st coat of paint complete
    Fire alarm wiring for both floors complete
Excavation 1.jpg

Asphalt for private road complete. Inspection complete.

NEXT WEEK'S ACTIVITIES

    2nd floor and 1st floor 2X4 light fixture installation in process
    Riser room FDC install. complete ceiling heads complete.
    Call for over head inspection on 2nd floor. Install boarders, and ready for ceiling install. also ready the 1st floor for overhead inspection
    Concrete stoop installed at riser room area exterior
    2nd coat of paint on 2nd floor.
Excavation 1.jpg

Tile work for 1st bathrooms complete, ready for toilets and sinks

Excavation 1.jpg

Casework in both floors ongoing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.