Weekly Project Update
The Learning Center Eanes isd

Martin Diaz
Jun 30, 2025
THIS WEEK'S ACCOMPLISHMENT
- Asphalt patch work on private road. Underground water line completed all the way to Camp craft. One test remaining.
- Both floors Casework is in progress.
- Bathrooms tile work on 1st floor complete
- Ceiling grid on 2nd floor minus stair area and the water fountain is complete
- 1st floor and 2nd floor 1st coat of paint complete
- Fire alarm wiring for both floors complete

Asphalt for private road complete. Inspection complete.
NEXT WEEK'S ACTIVITIES
- 2nd floor and 1st floor 2X4 light fixture installation in process
- Riser room FDC install. complete ceiling heads complete.
- Call for over head inspection on 2nd floor. Install boarders, and ready for ceiling install. also ready the 1st floor for overhead inspection
- Concrete stoop installed at riser room area exterior
- 2nd coat of paint on 2nd floor.

-
Tile work for 1st bathrooms complete, ready for toilets and sinks

Casework in both floors ongoing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.