Weekly Project Update
The Learning Center eanes isd

Martin Diaz
Jul 3, 2025
THIS WEEK'S ACCOMPLISHMENT
- 1st ceiling grid installation is done minus room 115 and the adjacent hallway due to the can lights not on site. Can't complete fur down
- All casework, on the 2nd floor and the 1st floor is complete,
- All back splash tile is complete
- 2X4 light fixtures on the 2nd floor are installed, minus over the stairway. 1st floor light fixture are in progress
- Sprinkler heads, HVAC grills and the audio speakers are in the process of being installed.
-

Finally we have lights
NEXT WEEK'S ACTIVITIES
- Scaffold for stairway area will be installed, and used by several trades to complete over the stairs. ie: HVAC grills, lights and sprinkler heads
- Fire riser room FDC will be installed and sprinkler lines will be tested. call for an inspection of sprinkler to prepare to close ceilings
- Over head electrical will be called in for inspection so we can install boarders
- 2nd coat of paint on 2nd floor walls, move to the 1st floor
- Overhead punch list walk with the VLK Engineers, before close the ceilings

- start flooring on the 2nd floor
Casework in lobby last item complete. Casework in both floors compelte

All back splash tile complete.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.