Weekly Project Update

The Learning Center eanes isd

Placeholder

Martin Diaz

Jul 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    1st ceiling grid installation is done minus room 115 and the adjacent hallway due to the can lights not on site. Can't complete fur down
    All casework, on the 2nd floor and the 1st floor is complete,
    All back splash tile is complete
    2X4 light fixtures on the 2nd floor are installed, minus over the stairway. 1st floor light fixture are in progress
    Sprinkler heads, HVAC grills and the audio speakers are in the process of being installed.
Excavation 1.jpg

Finally we have lights

NEXT WEEK'S ACTIVITIES

    Scaffold for stairway area will be installed, and used by several trades to complete over the stairs. ie: HVAC grills, lights and sprinkler heads
    Fire riser room FDC will be installed and sprinkler lines will be tested. call for an inspection of sprinkler to prepare to close ceilings
    Over head electrical will be called in for inspection so we can install boarders
    2nd coat of paint on 2nd floor walls, move to the 1st floor
    Overhead punch list walk with the VLK Engineers, before close the ceilings
Excavation 1.jpg
    start flooring on the 2nd floor

Casework in lobby last item complete. Casework in both floors compelte

Excavation 1.jpg

All back splash tile complete.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.