Weekly Project Update

The Learning Center

Placeholder

Martin Diaz

Jul 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete entire 2nd floor flooring
    Passed inspection fire sprinkler visual and Hydro.
    Install ceiling tile on 2nd floor minus ceilings that Can lights are missing
    Existing bathrooms Hard lids installed and started finish coat and prepare for paint
    Riser room completed the gyp work and start the tape and bed.
    1st floor ceiling tile installed.
Excavation 1.jpg

Hard lids on both existing bathrooms and new bathrooms getting finished

NEXT WEEK'S ACTIVITIES

    1st Floor install of LVT and carpet
    Install of Can Lights and close of ceiling both hard lid ceilings and drop ceilings
    Install of wall plates on entire building .
    Install hollow metal door in fire riser and Hardware on all doors
    Punch list walk
Excavation 1.jpg

2nd floor classrooms looking complete

Excavation 1.jpg

2nd floor carpet and LVT installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.