Weekly Project Update
The Learning Center

Martin Diaz
Jul 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete entire 2nd floor flooring
- Passed inspection fire sprinkler visual and Hydro.
- Install ceiling tile on 2nd floor minus ceilings that Can lights are missing
- Existing bathrooms Hard lids installed and started finish coat and prepare for paint
- Riser room completed the gyp work and start the tape and bed.
- 1st floor ceiling tile installed.

Hard lids on both existing bathrooms and new bathrooms getting finished
NEXT WEEK'S ACTIVITIES
- 1st Floor install of LVT and carpet
- Install of Can Lights and close of ceiling both hard lid ceilings and drop ceilings
- Install of wall plates on entire building .
- Install hollow metal door in fire riser and Hardware on all doors
- Punch list walk

-
2nd floor classrooms looking complete

2nd floor carpet and LVT installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.