Weekly Project Update

TCESD 2 STATION 6

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    Grade Beam Forms Underway
    Excellent Progress on Grade Beam Excavation
    Wastewater Tap at Manhole on Pleasanton Parkway
    Wastewater Line Installed and Covered on Pleasanton Parkway
    1st Manhole Installed at Weiss Ln.
    Storm Water Inlets Complete
Excavation 1.jpg

Pleasanton Parkway & Weiss Ln. Manhole

NEXT WEEK'S ACTIVITIES

    Reinforcing Steel for Grade Beams Install at LQ
    Close Up Grade Beams
    Excavate Remaining Grade Beams at AB
    Install Grade Beam Forms at AB
    Wastewater Line Install and Backfill on Weiss Ln.
Excavation 1.jpg

Wastewater Line Headed Up Weiss Ln.

Excavation 1.jpg

Grade Beam Form Progress

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.