Weekly Project Update
TCESD 2 STATION 6
THIS WEEK'S ACCOMPLISHMENT
- Grade Beam Forms Underway
- Excellent Progress on Grade Beam Excavation
- Wastewater Tap at Manhole on Pleasanton Parkway
- Wastewater Line Installed and Covered on Pleasanton Parkway
- 1st Manhole Installed at Weiss Ln.
- Storm Water Inlets Complete

Pleasanton Parkway & Weiss Ln. Manhole
NEXT WEEK'S ACTIVITIES
- Reinforcing Steel for Grade Beams Install at LQ
- Close Up Grade Beams
- Excavate Remaining Grade Beams at AB
- Install Grade Beam Forms at AB
- Wastewater Line Install and Backfill on Weiss Ln.

-
Wastewater Line Headed Up Weiss Ln.

Grade Beam Form Progress
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.